Boilermaker labour hire rates guide 2026

What does a boilermaker cost through labour hire? Start with the award minimum, add what the law and the insurer add, then see where a quote sits. Every number is sourced. Every assumption is yours to change. All of it is an estimate, not a quote.

  • Estimates only
  • Award rates from 1 July 2026
  • Not a quote

Award rates are minimums. Many Sydney sites pay more under an enterprise agreement.

Start with the award, not the ad

Job ads show a number. A labour hire quote shows a bigger one. The gap is not mysterious, and it is not all margin. This guide builds the number from the bottom so you can check any quote against it.

Where the bottom is. For many fabrication and manufacturing trades, the minimum pay is set by the Manufacturing and Associated Industries and Occupations Award. Its tradesperson level I (C10) is the reference classification in this guide, and the Fair Work Ombudsman pay guide has the current hourly rate for every level.1 The Fair Work Commission lifted award minimums by 4.75% from 1 July 2026.2 Which classification a boilermaker is paid at depends on their qualifications, their duties and the agreement that applies. Construction sites may sit under a different award, and many industrial sites run enterprise agreements that pay more.

What a labour hire provider adds. Casual loading, superannuation, workers compensation, payroll tax, insurances, PPE, induction, payroll and account management, and the provider's margin. The calculator below starts from what you pay a full-time boilermaker and adds each on-cost in turn, from sourced rates or placeholders you control. It leaves margin out, so the result is the cost of labour: what it costs to employ the person correctly as a casual, before the provider adds any margin. It is not a sell price.

Why that matters. If a quote sits below the floor for the same conditions, ask what has been left out. Cheap is usually missing a line.

At a glance

Award classifications compared, from 1 July 2026

Manufacturing and Associated Industries and Occupations Award, full-time and part-time adult rates. Each level is shown as a percentage of C10 tradesperson level I, the reference for this guide. Casual employees add 25%. The Fair Work Ombudsman pay guide has the current hourly rate for each level.

C10 tradesperson level I100%1The reference level. Casual adds 25%
C9 tradesperson level IIAbout 103%1Of the C10 rate. Casual adds 25%
C8 tradesperson special class level IAbout 106%1Of the C10 rate. Casual adds 25%
C7 tradesperson special class level IIAbout 109%1Of the C10 rate. Casual adds 25%
C6 advanced engineering tradesperson level IAbout 115%1Of the C10 rate. Casual adds 25%

Which level applies to a boilermaker depends on qualifications, duties and the agreement that covers the site. These classifications set minimums, not market rates.

At a glance

Shift, weekend and holiday rates for a C10 tradesperson

Shown as a percentage of the base rate. Full-time employee, from 1 July 2026. Same award, same pay guide.

Afternoon or night shift115%1Of base. Five or more successive shifts
Permanent night shift130%1Of base
Saturday150%1Of base. Ordinary hours by agreement
Sunday200%1Of base. Ordinary hours by agreement
Public holiday250%1Of base. Ordinary hours by agreement
Overtime, Monday to Friday150%, then 200%1Of base. First three hours at time and a half, then double time

Allowances (for example height, confined space, industry or site allowances) can apply on top. See the pay guide and your agreement.

What moves a boilermaker's rate

DriverMoves the rateWhy
Classification and agreementUpA higher level or an enterprise agreement sets a higher base
Casual or permanentCasual is 25% higherCasual loading replaces paid leave
Shift patternUp for nights, weekends and public holidaysShift loadings and penalty rates
Overtime and long shiftsUpTime and a half for the first three hours, then double time
AllowancesUpHeight, confined space, industry and site allowances where they apply
Tickets and weld codesUp in a tight marketScarce tickets and coded welding command a premium
Duration and volumeDownA longer, steadier engagement can lower the margin per hour
Location and travelUpRegional work adds travel and accommodation
NoticeUpShort-notice cover costs more to find

Shutdown and night work

Shutdown ads often show higher hourly figures than day-shift maintenance ads. Some of that is the work. Most of it is arithmetic: night loadings, overtime on long shifts, public holidays and allowances stack. Put them into the calculator below and you will see the same shape.

Same job, same pay

Where the Fair Work Commission has made a regulated labour hire arrangement order, labour hire workers doing the same work as the host's direct employees must receive at least the host's protected rate of pay.3 If a host agreement pays more than the award, the award figures above are not the floor for that site.

Calculator

Full-time rate to labour hire cost calculator

Enter what you pay a full-time boilermaker per hour. The calculator shows what the same person costs as a casual through labour hire, step by step: the 25% casual loading, shift and overtime penalties, super, workers compensation, payroll tax and other on-costs. The result is the cost of labour, not a sell price. Any labour hire provider adds its margin on top of this figure.

Your full-time rate

The base hourly rate on your own payroll, before super, loadings or overtime. Use your real figure: award, agreement or above-award.

Pay

In this model a shift loading applies to weekday ordinary hours only.

Shift and hours

The first three hours of overtime in a day.

Overtime after the first three hours in a day.

Height, confined space, industry or site allowances from your agreement, as a share of the full-time hourly rate. Zero if none.

Advanced: on-costs

Placeholder, not a sourced rate. Your policy rate depends on industry class and claims history. Ask your insurer or broker.

A provider above the threshold pays payroll tax on wages and super and builds it into the rate.

Placeholder. Insurances, PPE, induction, payroll and admin. Replace with your own figure.

Results at the inputs shown

Cost of labour per hour, casual through labour hire Estimate
$0.00

What it costs to employ this person correctly as a casual: wages, loadings, super, workers compensation, payroll tax and other on-costs. This is the cost of labour, not a sell price. A labour hire provider's margin is added on top.

Step 1. Casual base rate: your full-time rate plus 25% casual loading Estimate
$0.00
Step 2. Wage per hour after shift, weekend, overtime and allowances (includes step 1) Estimate
$0.00
Step 3. Plus super guarantee per hour (12% of ordinary-hours pay) Estimate
$0.00
Step 4. Plus workers compensation per hour Estimate
$0.00
Step 5. Plus NSW payroll tax per hour (5.45% of wages and super) Estimate
$0.00
Step 6. Plus other on-costs per hour (insurances, PPE, induction, payroll) Estimate
$0.00
Cost of labour above your full-time base rate Estimate
—
Cost of labour for the week Estimate
$0

Before any labour hire margin.

Estimate only. This is not a quote and it is not Smart Industrial's rates. It is the cost of labour for the rate you enter, under the Manufacturing Award loadings and the assumptions above, before any labour hire margin. A real quote depends on the agreement, classification, shift pattern, tickets, site and duration.

Assumptions

AssumptionValueNote
Your full-time rateThe figure you enter. The calculator does not use or show Smart Industrial's rates You can change it above
Casual loading25%1 Fixed
Shift loadings and penalty rates15% and 30% shift loadings. 150%, 200% and 250% for Saturday, Sunday and public holidays. Overtime 150% for three hours, then 200%1 Fixed
Superannuation guarantee12% of ordinary-hours pay (overtime and allowances are left out: a simplification)4 Fixed
Payroll tax, NSW5.45% of wages plus super above the annual threshold set by Revenue NSW, 2026-275 You can change it above
Workers compensation3.5% of wages. Placeholder You can change it above
Other on-costs2% of wages. Placeholder You can change it above
Provider marginNot included. The result is the cost of labour, before any provider margin Fixed

What the numbers leave out

  • Penalty rates here apply to ordinary hours worked on that day by agreement. Shift loadings apply to weekday ordinary hours only.
  • Real engagements add minimum shift lengths, travel, tool and meal allowances and site-specific conditions.
  • Enterprise agreements and other awards differ, often upwards. Where a regulated labour hire arrangement order applies, the host's rate is the floor.
  • Superannuation rules changed from 1 July 2026 (Payday Super). Check how your payroll calculates super.

Checklist

Check any quote against the floor

Print this and hold your next labour hire quote up to it. A good provider answers every line without a fuss.

How it works

How we quote a boilermaker

No rate card, because a number without a brief is wrong for most clients.

01

Send the brief

Trade and level, tickets and weld codes, shift pattern, site, start date and duration. Request boilermakers or call 02 7813 4761.

02

We confirm the base

We confirm which award or enterprise agreement applies and the classification the work calls for.

03

You see the build-up

Rates are built on the applicable award. We show the build-up line by line on request: base, loadings, on-costs and margin.

04

You approve the profiles

Verified qualifications, tickets and experience, then timesheets you approve and weekly invoices auto-generated from them.

Smart Industrial is first class in delivering projects, labour and engineering support across all facets of the industrial space.

★★★★★Gavin Jones30 April 2024Google review

Questions

Boilermaker rate questions

What is the award rate for a boilermaker in NSW?

It depends on the award or agreement that covers the work. Under the Manufacturing Award, the tradesperson level I (C10) is the base classification, and higher levels (C9 down to C6) are paid progressively more. The Fair Work Ombudsman pay guide sets out the current hourly rate for each.1 Construction sites may sit under a different award, and many industrial sites pay more under an enterprise agreement. Treat award figures as the floor, not the market.

Why is a labour hire rate so much higher than the award rate?

Because the award rate is only the wage. Casual loading adds 25%, then come superannuation at 12%, workers compensation, payroll tax, insurances, PPE, induction, payroll and the provider's margin. With the calculator's placeholder on-costs, the cost of labour before any margin is about 55% above the full-time base rate. Margin sits on top of that.

Do boilermakers and welders get paid the same?

Not automatically. A boilermaker holds a fabrication trade and a welder joins metal. Classification follows qualifications and duties, and agreements differ. See our boilermaker and welder pages for how we match the trade to the brief.

Do you publish your rates?

No. Rates depend on the award or agreement, classification, shift, site, tickets and duration, so a published number would be wrong for most clients. We build the rate on the applicable award and show the build-up line by line on request.

What about shutdown and night rates?

Shutdown work stacks loadings: afternoon and night shift loadings, overtime on long shifts, weekend and public holiday rates and allowances. Put them in the calculator and the hourly figure rises quickly. An ad that shows a high hourly rate for a shutdown is usually showing that stack, not a base rate.

Does 'same job, same pay' change the numbers?

It can. Where the Fair Work Commission has made a regulated labour hire arrangement order, labour hire workers must receive at least the host employer's protected rate of pay for the same work, which can lift the rate above the award.3 Our rates are built on the applicable award and the site's requirements, and we will tell you if an order applies to your site.

Is the calculator a quote?

No. It is an educational estimate built from public award rates and placeholders you can change. It does not show our rates or our margin. For a quote against a real brief, request boilermakers.

Sources and notes

  1. Fair Work Ombudsman: Pay Guide, Manufacturing and Associated Industries and Occupations Award [MA000010]. Effective from the first full pay period on or after 1 July 2026; published 29 July 2026. Base classifications C10 to C6, casual loading, shift loadings and penalty rates for the Manufacturing Award. Accessed 3 October 2026.
  2. Fair Work Commission: Annual Wage Review 2026 decision. 4.75% increase to modern award minimum wage rates from 1 July 2026. Accessed 3 October 2026.
  3. Clayton Utz: Same job, what pay? Guidance on new labour hire laws. Law-firm commentary on regulated labour hire arrangement orders, which the Fair Work Commission has been able to make since 1 November 2024. Accessed 3 October 2026.
  4. Australian Taxation Office: Key superannuation rates and thresholds. Superannuation guarantee rate of 12% from 1 July 2025. Accessed 3 October 2026.
  5. Revenue NSW: Payroll tax thresholds and rates. 5.45% above the annual threshold in 2025-26 and 2026-27. Accessed 3 October 2026.